A typical membrane plant installation project within an existing plant building can be delivered and commissioned within approximately six to seven months from order placement, depending on project complexity, site conditions, and equipment lead times. Knowing what happens in each phase helps operations and engineering teams plan around it with confidence, rather than treating the timeline as a black box.

Design and Engineering (3-6 Weeks)

Every project starts with a detailed design and engineering phase. Process and instrument drawings (P&ID) are drafted and approved, and plant layout requirements, hydraulic design, footprint constraints, utilities availability, and integration requirements are confirmed. This is also where long-lead items - membranes, pressure vessels, pumps, shell and tube heat exchangers, instrumentation, and control logic hardware - are identified and locked in. Getting these on order early protects the overall project schedule and avoids procurement delays further down the line.

Fabrication and Construction (8-12 Weeks)

Once long-lead items are underway and tracking on the critical path, fabrication and construction of the membrane skids can be planned and executed with partnered sub-contracted parties. SMS coordinates equipment procurement, quality and assembly, and workshop pre-commissioning and acceptance testing where required. Completing this work off site, rather than in the plant, is what keeps the on-site programme short.

Shipping and Site Preparation

Once manufacture is complete, equipment is shipped to site and prepared for installation. Logistics are planned to align with construction progress and the client's site access and operational requirements, so equipment arrives when the site is genuinely ready for it.

Installation, Integration and Commissioning (4-8 Weeks)

The final phase - skid installation, integration with the existing or new facility, and commissioning - is carefully coordinated with site teams to minimise disruption and achieve a smooth transition into operation.

Minimising Downtime and Operational Impact

Protecting production is a constant thread through every phase, not just an afterthought at handover:

  1. SMS works closely with customers to schedule critical installation activities around planned plant shutdowns, maintenance windows, and seasonal production requirements wherever possible.
  2. A modular, skid-mounted approach reduces on-site construction time by completing as much fabrication and testing off site as possible before equipment arrives.
  3. Pre-assembled process modules, pre-wired control systems, and off-site testing significantly reduce installation risk and compress commissioning schedules.
  4. Where brownfield integration is required, SMS develops detailed cutover and commissioning plans to minimise process interruptions and maintain operational continuity.
  5. Commissioning support follows a structured process - decontamination, water commissioning without membranes, optimisation, operator training, performance verification, and handover documentation - so the plant reaches design performance quickly.
  6. SMS remains engaged beyond startup, providing technical support and operational guidance to help site teams maximise membrane performance and system reliability from day one.

Six to seven months sounds like a long runway, but most of it is protecting the parts of the project that are hardest to compress: engineering sign-off, long-lead procurement, and off-site fabrication. Getting these sequenced correctly at the outset is what keeps the on-site installation window short and predictable.